Construction Timeline

SUMMER 2017

  • Periodicals & Electronic Resource Services moves from 6th floor to 4th floor
  • Art Resource Lab moves from 5th floor to 6th floor
  • 50 Computer workstations move to the 6th floor

Fall 2017

  • Periodicals and Resource Services reopens
  • E404 Opens as a Forecast/Library Instruction Room
  • 6th floor space reopens as open work space with a maker space, computing resources, art resources

 

Completed Projects

SPRING 2017

  • SPARC reopens in renovated space
  • AMS unit moves into renovated space

SPRING 2016

Demolition and construction begin in 4th & 6th floor construction sites
25 student computer workstations and 6 scanners available on the 4th floor public space during library hours
SPARC resumes operations

WINTER 2016

  • 4th floor library services are temporarily closes
  • Elevator access to the fourth floor is suspended until project completion
  • Special Collections Resources and Offices move to temporary space